Work continues on ruptured 36-inch transmission pipeline on the Mosquito Creek

By Shirvan Williams

Restorative work is proceeding as scheduled at the site of the ruptured 36-inch transmission pipeline, at Godineau Bridge, Mosquito Creek, San Fernando, according to the Water and Sewerage Authority.

WASA has revealed that team members working overnight have completed fabrication works on the southern side of the structure with installation and final welding in progress. As for the northern side, installation and adjustments are underway, with the straight run of a pipeline also in the installation phase as scheduled.